Curbing installed on north side of SE 47th Terr from Coronado Pkwy east toward 8th CT

Crews have begun work installing curbing on the north side of SE 47th Terrace from Coronado Parkway east toward 8th Court. Crews have made significant progress on the installation of pavers on the south side of SE 47th Terrace in that block, which gives some insight into what the finished multimodal pathway will look like.

Crews install pavers along the south side of SE 47th Terrace from Coronado Parkway to 8th Court.
Crews install pavers along the south side of SE 47th Terrace from Coronado Pkwy to 8th CT.

Crews are progressing with forming the curb on the north side of SE 47th Terrace, pouring the concrete for the ribbon and F curb, which will provide the framework for the new pavers. Crews will continue work on the curbing on the north side of SE 47th Terrace and continue installation of pavers on the south side of SE 47th Terrace next week.

These widened pathways will allow for the community to walk and bike along SE 47th Terrace once the project is complete.

Crews pour concrete for new curbing on the north side of SE 47th Terrace from Coronado Parkway toward SE 8th Court.
Crews pour concrete for new curbing on the north side of SE 47th Terrace from Coronado Parkway toward SE 8th Court.

As the project team finalizes underground utility work in each block, then the project team will begin grading the site in preparation for installation of the curbing.